We made it to February!

January seem to last forever, bring on February! We made it through the first month of the year with minimal snow just dustings but some very cold weather. Today is still brisk 19 degrees but our men continue to work hard.

On East Chop we have one project finishing up and the other due to be completed in June. The Winemack home has had all the kitchen and bathroom hardware installed. The smoke inspection has been completed. The pluming and electrical inspections are in progress. We hope the owners will be moving in soon. Final photos of the project will be posted on our website.

On East Chop Drive the renovation project continues with framing for new windows. The bathroom walls are being built along with the new closets.

Moving along to our newest project off Barnes Road we set a home on Monday. Things went quick and smoothly just how we like it. The contractors are currently buttoning up the outside of the home. Next they will start on the exterior trim and siding.

In Vineyard Haven on Mayflower our contractors have completed the great room walls and roof and that is all closed in. Looking more like a home now.

Lastly up in West Tisbury at the Trotter’s Lane site we are waiting on the septic to be installed.

Stay warm and see you next week!