Sunshine and 50’s in February!

Sunny and in the 50’s today, great day to be working outside in February in New England.  As always we have bunch of jobs going on in all different stages.

Starting with Chamber’s Way, Edgartown the foundation has been backfilled, sill plates going in early next week and the modular will arrive on island on Wednesday. The forecast is looking good for set day in the 40’s and sunny.  Set pictures to follow!

 

60 Curtis Lane is in the final building inspection called in.  Certificate of occupancy to follow! Owners will be able to move all their furniture in and start enjoying their new home! This home had a number of custom add ons like the custom desks and floating shelves, the mudroom with built-ins and fireplace.  Cannot wait to see what it looks like with the owners touches!

 

 

 

Moving on to 50 Curtis Lane, Edgartown the painters are in progress, the interior trim is being installed. Here are some progress photos.

 

In Vineyard Haven, off Franklin Street the contractors are shingling and working on the exterior decking.  Rough plumbing and heating and electrical all complete. Insulation and drywall coming up next.

 

Enjoy the sunshine and have a great weekend!