We are seeing progress on our jobs even with two person crews. Starting next week the towns on island passed that five workers can be on a job site which will make things go a little faster. It was a challenging but we have made progress and held to the guidelines. Longer days, weekends and swapping crews through scheduling have definitely helped. We hope everyone continues to being safe and practicing social distancing, wearing masks and washing hands.
In Oak Bluffs on Spruce Ave. the tile has been installed in the bathrooms, the details on the decks are coming together.
Up in West Tisbury things are coming along…the decking and outside shower have been completed. Bathrooms have been tiled and hardware will be going up soon.
If you are thinking about doing a modular now could be the time to start planning while you are working from home and noticing all the changes that need to be made.
Stay tuned to next weeks progress with more workers on our various job sites!