Labor Day on MVY

Labor Day is around the corner.  The summer is coming to an end.  We made it!  It was busy and different this year with the pandemic but we survived and continue to work hard.

The pool and fencing are in progress on Hampson Ave.  Final photos to come upon completion.  The owners on Spruce Ave are enjoying their new home.

Up on West Chop the dehumidifiers are in place acclimating for the wood floor install scheduled to start next week.  The trim and baseboards going in to bathrooms.

 

At the latest set in Katama the work continues to button up the house.  Exterior and subs have started their roughs inspections.

The Vineyard Montessori School in Vineyard Haven is expanding and the foundation is foundation is in place.  The modular set is due to come to the island mid October.

 

Have a happy and safe Labor Day weekend coming up!