The Ground hog did not see his shadow which predicts an early spring. Lets’s hope he is correct. This week flew by! Here is our weekly progress report.
At the Mayflower Lane project in Vineyard Haven the owner was on site this week to meet with the contractors to go over design work and finishes.
Up in West Tisbury on Trotter’s Lane the septic was installed and passed inspection woohoo for progress. Now the front steps and decking are in progress. Once the work is complete we will call in our final inspections.
Back down island in Oak Bluffs we have three current jobs going on. At our renovation project the windows are still going in and insulation has begun. The big item this week was the rat slab was poured. Here are some photos from today.
Next we have the Winemack home which is very close to being completed. We are waiting on the certificate of occupancy and then the owners will soon be able to enjoy their new Vineyard home. Final photos will come next week!
Lastly we have the Barnes Road site where the house was set last week. The crew is currently working on the exterior of the home. The electrical and rough plumbing are underway.
Have a great weekend everyone and see you next week!